
![]() Temporary Sheeting Installation |
National Grid’s Remediation Contractor continued with site remediation activities, which included the delivery of construction materials, imported backfill material (stone and common fill), and construction equipment and supplies. Shallow Excavation Area remedial activities at Tent Position #6 with off-site transport and disposal of impacted soils at approved and permitted disposal facilities were completed. Placement of imported clean backfill material and compaction testing within the Tent Position #6 Shallow Excavation Area were also completed. Installation of temporary sheet piles continued at planned tent positions along the northern site perimeter. National Grid’s consulting engineer conducted noise and vibration monitoring activities, as necessary.
Maintenance of the decontamination areas, work zones, on-site gravel access roads, parking areas and material staging areas, the imported backfill material (i.e., clean fill) stockpile covers, the perimeter privacy screen, and soil erosion and sediment control (SESC) measures continued. Odor and dust suppression activities were conducted, as necessary. National Grid’s consulting engineers continued to monitor the site activities with the fixed base community air monitoring program (CAMP) equipment, as well as with noise and vibration monitors.
![]() Backfilling operation at Tent Position 6 |
During the period from November 16, 2009 through November 22, 2009, six fixed base CAMP units and one portable CAMP unit were in-use and measured total volatile organic compounds (TVOC) and particulates (PM10). Fifteen-minute averages for both TVOC and PM10 data remained in the Operational Condition. No TVOC and PM10 measurements above the Action Level were reported for the weekly CAMP monitoring period. Weekly Reports of the CAMP data can be found as a separate tab in the Weekly Report Archive section.
For the holiday week of November 23, 2009 through November 25, 2009, Tent Position # 6 will be relocated north to Tent Position # 7. Tent relocation activities will include the temporary disassembly and staging of tent anchors and the vapor management system (VMS), temporary removal of the central panel, end panels and access doors, followed by the relocation of the two tent sections and replacement of the two access doors and central panel. The temporary fabric enclosure supports, tent anchors, and VMS will be reset as the final phase of the tent position relocation. Odor and dust suppression activities will be conducted as necessary. Work zone delineation, site maintenance activities, CAMP operation, and noise and vibration monitoring activities will continue.