Weekly Update Ending: July 09, 2010

photo
Grout Cube Sample Collection

National Grid’s Remediation Contractor continued with site remediation activities, which included the delivery of construction materials, imported backfill material (stone and common fill), as well as construction equipment and supplies. On-site Waterloo BarrierTM interlocking steel sheet piling flushing and grouting operations continued. Tent Position #15 Shallow Excavation activities continued with off-site transport and disposal of impacted soils at approved and permitted disposal facilities.  Common fill material deliveries and final grading and cap installation activities continued to progress in the central and eastern parts of the Site.   National Grid’s consulting engineer conducted noise and vibration monitoring activities, as necessary.

Maintenance of the decontamination areas, work zones, on-site gravel access roads, parking areas and material staging areas, imported backfill material (i.e., clean fill), stockpile covers, the perimeter privacy screen, and soil erosion and sediment control (SESC) measures continued. Odor and dust suppression activities were conducted, as necessary. National Grid’s consulting engineers continued to monitor the site activities with the community air monitoring program (CAMP) equipment.

During the period from July 5, 2010 through July 11, 2010, six fixed base CAMP units and two portable CAMP units were in-use and measured total volatile organic compounds (TVOC) and particulates (PM10). Fifteen-minute averages for both TVOC and PM10 data remained in the Operational Condition.  No elevated TVOC or PM10 readings were reported for the weekly monitoring period.  The Weekly Report that summarizes the CAMP data can be found as a separate tab in the Weekly Report Archive section.

For the week of July 12, 2010 through July 16, 2010, cap material deliveries along with final grading and cap installation activities are scheduled to continue in the central and eastern part of the Site.  Tent Position #15 Shallow Excavation activities are scheduled to be completed with off-site transport and disposal of impacted soils at approved and permitted disposal facilities. Delivery of imported clean backfill material (stone and common fill) and backfill material placement and compaction are also scheduled to continue inside Tent Position #15.  Flushing and grouting operations of the on-site Waterloo BarrierTM interlocking steel sheet piling are scheduled to be completed. Odor and dust suppression activities will be conducted, as necessary.  Work zone delineation, site maintenance activities, CAMP operation monitoring activities will continue, and noise and vibration monitoring activities will continue, as necessary.