Weekly Activities
For the week of March 7, 2016, National Grid’s contractor will complete re-mobilize to the site to continue the remedial construction in the bulkhead area. This will include re-exposing the barrier wall so the sheet joints can be cleared and grouted. Mobilization associated with the coring into the top of the tunnel that runs perpendicular to Beach Channel Drive is complete. The activities for this week will include putting holes into the top and the pumping of grout into the tunnel.